MOTET / Retrofit field guide

How to Replace the Inner Membrane of a Double Membrane Gas Holder — Part 2

From dual sealing interfaces and new inner-membrane installation to outer-membrane reinstatement, controlled inflation and leak acceptance

14 min read

Retrofit field guide / Double membrane gas holder

Double membrane gas holder after inner-membrane replacement and controlled inflation
Figure 1. Completed field condition. This article continues from removal of the failed inner membrane and records installation, outer-membrane reinstatement, inflation and acceptance.

Part 1 ended with the failed inner membrane removed and the base membrane, anchor channel, clamping hardware and interfaces exposed. Part 2 is not simply about putting a new membrane back; it is about rebuilding a continuous, inspectable and verifiable sealing and load-transfer system.

Review inner-membrane replacement Part 1

Installation and acceptance chain

  1. 01Base released
  2. 02Lower seal
  3. 03Inner membrane
  4. 04Upper seal
  5. 05Outer reinstated
  6. 06Instrumentation
  7. 07Staged inflation
  8. 08Leak acceptance

Safety and scope

This article explains sequence and quality control; it does not replace a site-specific method statement, permit to work, gas testing, energy isolation, lifting plan or local law. EPA AgSTAR treats inspection, maintenance, records and safety as core biogas-system practices, while OSHA 1910.147 requires control and verification of hazardous-energy isolation before maintenance. Approved project documents and local requirements govern the work.

EPA AgSTAR · OSHA 1910.147

1. Base Release and the First Continuous Sealing Strip

Before the new membrane enters the work area, the base membrane, foundation edge, anchor channel, flange faces and studs should be released as a hold point. Remove hard residue and standing liquid, eliminate sharp edges and verify the flatness and continuity of reusable clamping parts. The first continuous sealing strip is installed only after this interface is accepted.

The strip is not an improvised gap filler; it is part of the compression seal. Corners, overlaps, holes and joints must remain continuous and traceable. Material, profile, jointing method and target compression follow the approved drawings and supplier documentation.

New inner membrane delivered and folded for installation
Figure 2. The new inner membrane remains in a controlled fold while the reinforced perimeter, prefabricated holes and lifting slings are checked before lifting.

2. Lift, Orient and Unfold the New Inner Membrane

Before lifting, verify the membrane centre, interface orientation, installation datum and sling condition. The lifting arrangement controls the unfolding path; no single fitting, weld or perimeter flange should carry the full load. Lower the bundle slowly under ground guidance to avoid rails, studs and sharp steelwork.

Inspection of new inner-membrane slings and lifting points
Figure 3. Sling distribution, bundle restraint and load direction are verified so lifting hardware cannot bite into the membrane.
New inner membrane lowered to the gas-holder base centre
Figure 4. The bundle is lowered under control near the base centre, preserving room for radial unfolding in the planned orientation.

Establish the centre and primary interface orientation before releasing each folded zone. Personnel stay on suitable walk areas and move the membrane with soft handling points, keeping footwear, tools and drag loads away from welds and fitting roots.

New inner membrane opening under control of the central lifting point
Figure 5. Light tension at the central lift point allows the membrane to open from the centre outward without uncontrolled piling.
New inner membrane spread radially across the circular base
Figure 6. Major twist is removed before perimeter detailing; local force is not a substitute for overall centring.

3. Perimeter Alignment, the Second Seal and Staged Clamping

After the reinforced perimeter lands on the lower strip, verify orientation and hole positions from defined datums, then work in opposing sectors. Marking and hole checks establish the actual geometry; they do not mean tightening each visible hole immediately. If error accumulates, return to centring and membrane lay rather than forcing the edge.

Marking and checking hole positions along the reinforced inner-membrane edge
Figure 7. Alignment marks control circumferential error and fastening sequence; they are not permission for uncontrolled site enlargement of holes.
Progressive fastening of the inner-membrane perimeter to the studs
Figure 8. Fastening moves progressively from positioning to compression in an approved symmetric sequence without locking one local sector first.

After the inner membrane passes its hold point, the second continuous sealing strip is placed above it before the retained outer membrane is reinstated. This creates an auditable stack—support surface, lower strip, new inner membrane, upper strip, retained outer membrane and clamping hardware—subject to the approved project drawings.

Reinforced inner-membrane perimeter and fastening-point detail
Figure 9. The reinforced edge, holes and circumferential sealing path remain continuous and free from trapped wrinkles or debris.
Factory-prepared reinforcement and weld detail on the new inner membrane
Figure 10. Regular reinforcement and continuous weld geometry support traceability and visual review; final acceptance also depends on supplier inspection records.
New inner membrane after perimeter positioning and fastening
Figure 11. A continuous perimeter is established and the centre, main interface orientation and wrinkle distribution are checked again before the outer membrane covers the work.
Second continuous sealing strip positioned between membrane layers
Figure 12. The continuous strip follows the circumferential interface. It must remain clean, unbroken and untwisted, with compression controlled by the approved design.

4. Reinstate the Retained Outer Membrane in Its Original Orientation

The retained outer membrane lifted in Part 1 is returned only after the new inner membrane and upper sealing strip pass inspection. Original orientation marks, fitting direction and lifting points are checked, while ground guidance controls folds and prevents contact with rails, sharp edges and the new inner membrane.

Retained outer membrane lifted back above the base
Figure 13. The outer membrane remains a reusable finished component; lifting speed, wind conditions and ground guidance stay controlled.
Initial condition after lowering the retained outer membrane over the new inner membrane
Figure 14. Centre and fitting orientation are confirmed before releasing folds by sector without dragging the concentrated bundle over the new membrane.
Retained outer membrane respread and centred around the circumference
Figure 15. The outer membrane is opened from the centre outward, matching fittings, air duct and instruments to the original orientation marks.
Perimeter clamping hardware and fastening points after reinstatement
Figure 16. The clamping hardware continuously covers the sealing path and is tightened in the approved sequence. A photograph does not replace torque or fastening records.

5. Restore Penetrations, Level Signals and Wiring

After clamping, restore the level instrument, pressure tapping, air duct and cables using the removal records. Reconnection is more than joining wires: verify terminals, polarity or signal definition, strain relief, sealed glands, flange fastening and water-shedding path, then complete the loop check.

Signal cable being reconnected to the level-measurement fitting
Figure 17. After terminal connection, cable restraint, sealed entry and signal response still require verification; tape is not a substitute for an engineered seal and strain relief.

6. Staged Inflation: Form, Observe and Verify

First inflation must be a controlled process that can be stopped at any time. Establish support air and allow the outer membrane to form gradually while inspecting the perimeter clamp line, air duct, fittings and wrinkle migration. Stop for abnormal rubbing, local tension, fitting movement or implausible pressure and level signals.

Support-air duct connected at the start of low-stage inflation
Figure 18. The initial stage remains slow and observable while checking that the duct, membrane layers and perimeter interfaces are neither pulled nor trapped.
Outer membrane gradually forming its profile during staged inflation
Figure 19. Shape checks focus on symmetry, wrinkle migration and hard contact. One photograph records a moment; it does not replace continuous inspection.

7. Foam-Solution Leak Checks, Functional Tests and Final Acceptance

Once the membrane form is stable, apply a membrane-compatible foam leak-detection solution to accessible flanges, penetrations, pressure taps and other approved test points. Persistent bubble growth indicates a possible leak that must be marked, depressurised, corrected and retested. The absence of audible leakage is not acceptance evidence.

Then verify support-blower changeover, pressure and level signals, alarms and interlocks, recording shape and operating trends under the project-defined condition. Test medium, pressure, stabilisation time and acceptance criteria come from the approved procedure; this article does not substitute generic values.

Front elevation of the gas holder after inflation
Figure 20. The final profile is assessed together with pressure, level, blower and interlock records; a rounded shape is only one part of acceptance evidence.
Membrane flange included among foam-solution leak-check points
Figure 21. The photograph records a flange and fastening interface that requires focused inspection. Application, observation and retest results are documented separately.

Six common errors

  • Covering hard debris, standing liquid or sharp edges with the new membrane.
  • Allowing the sealing strip to break at corners, overlap unpredictably or be cut by bolt holes.
  • Forcing hole alignment from one point and transferring wrinkles and eccentricity around the circumference.
  • Fully tightening a local group of bolts instead of using a symmetric staged sequence.
  • Dragging the retained outer membrane over sharp edges or allowing lifting gear to crush it.
  • Accepting a rounded final shape without verifying signals, alarms, interlocks and leakage records.

Final acceptance record

  • Lower and upper sealing strips are continuous, compatible and follow a clear compression path
  • Inner-membrane orientation, centre and perimeter hole alignment are recorded
  • Pressure bars, fasteners and tightening sequence follow the approved documents
  • Inner-membrane seams, flange edge and penetrations pass visual inspection
  • The retained outer membrane has no new abrasion, trapped folds or hard contact
  • Blower, pressure, level, alarm and interlock signals are checked
  • Membrane form remains stable without abnormal rubbing during staged inflation
  • Accessible interfaces pass documented foam-solution leak checks

Professional handover is not defined by “the holder inflated.” Every interface hidden by the next layer must have been inspected, recorded and released, with final form, leakage results and control signals supporting the same conclusion.

Frequently Asked Questions

Why are sealing strips installed on both sides of the membrane flange?

The lower and upper continuous strips create controlled compression interfaces between the support surface, membrane flange and retained outer membrane. Their material, section and compression must follow the approved design.

Can misaligned bolt holes be pulled into position from one point?

No. The membrane should be centred and aligned progressively around the circumference. Forcing one local point can transfer wrinkles and stress into the membrane, welds and penetrations.

Can the retained outer membrane be reinstalled immediately after the inner membrane is fixed?

Only after the inner membrane, seams, flange, sealing strip, penetrations and clamping sequence have passed the defined hold-point inspection.

What should be checked while the gas holder is inflated?

Observe membrane shape, wrinkle migration, contact with nearby steelwork, blower response, pressure and level signals, alarms and interlocks throughout staged inflation.

How is foam solution used during leak checking?

Apply an approved compatible solution to accessible test points under the specified test condition. Persistent bubble growth indicates a possible leak that must be corrected and retested.

Does a normal final shape prove the replacement is complete?

No. Final acceptance also requires documented sealing, fastening, instrumentation, alarm/interlock, leakage and operating checks under the project procedure.

Inner-membrane replacement and acceptance inquiry

Turn every hidden interface into verifiable engineering evidence.

Share the gas-holder arrangement, dimensions, gas service, failure photographs, shutdown window and control information. MOTET can define the replacement, sealing review, reinstatement and acceptance scope.

Contact our engineering team

Related insights

Inner Membrane Replacement (Part 2) | MOTET